Construction Update June 2008
Construction Update June 2008Tyndall New Laboratory Building
Construction Update June 2008 current activities:
- RC main frame completed
- Commencing 1st fix mechanical and electrical works first floor
- Commenced installation of clean room on ground floor
- Plant room and atrium steel delivered to site
- Removal of Galbestos cladding Block B
- Contined installation of underground services within Atrium ground floor
- Close-out of the summer shutdown works
- Completion of new CHW piping runs in Block A and loading platform for AHU replacement
Upcoming works:
- Erection of Block C roof plant rooms and complete permanent roof finishes
- Commence M & E fit out to ground floor and 3rd floors and contine installation on 1st floor
- Commence 2nd fix M & E to basement area
- Progress internal room partitions on each floor
- Continue external finishes to Block B & C
- Continued works within the new Atrium area and structural upgrades at high level
- Start erection of Atrium passenger lift and stairwell structural steel
- Complete summer shutdown